Dickenson Road Sanitary Sewer Plan for week of Aug 12th


map of Dickenson Road sanitary sewer plan
Dickenson Road Sanitary Sewer Road plan map

Here is the schedule for this week for the Dickenson Road Sanitary Sewer installation: 


Shaft #1    Regional Road 56 and Golf Club Road

-tunneling from shaft #1 to Shaft #2 is ongoing, contractor is working 2 shifts

Shaft #2   Located west of house #3458 Golf Club Road

-no work at this location, single lane of traffic is open to residents at this location.

 Shaft #3      Golf Club Road and Trinity Church Road

-the contractor is continuing to mobilize the Micro-tunneling equipment to this location   

Shaft #4     Dickenson Road and Nebo Road

-the contractor will be drilling and breaking rock to advance the starter tunnel (2 shifts)

Shaft #5 - Dickenson Road, approximately 385m east of Glover Rd

-no work scheduled at this location

Shaft #6    Dickenson Road and Nebo Road

-no work scheduled at this location


Maintenance Hole 32A   Dickenson Road and Glover Road

-no further work at this location this week

Maintenance Hole 33A  Dickenson Road between Trinity Church Road and Glover Road

-no further work at this location this week

Maintenance Hole 26A  Dickenson Road between West of Nebo Road

-Preparation of site compound

Maintenance Hole 27A  Dickenson Road between West of Nebo Road

- Mob Drill and Set up Guide Walls, Bell Relocation.

Open Cut Sewers – Miles Road to Upper James

-Subcontractor is installing the sewer pipe in the open cut trench in the vicinity of French Road and Dickenson on the west side  


All road closures still remain in effect, Miles Road to Upper James on Dickenson is closed to thru traffic, travel is still open for residents, city services, EMS and school buses. 

Communication is being made with city services, EMS and school buses when the closure points are moved as the work progressed westerly towards Upper James.  

 

Note: starting Tuesday August 6, the north bound lane on Upper James will be closed for the next 6 to 7 weeks for construction.  The closure will be starting south of Dickenson Road and finish on the north side of Dickenson Road.