top of page
marktadeson

Dickenson Road Sanitary Sewer Update: July 23


 

Shaft #1    Regional Road 56 and Golf Club Road

-tunneling from shaft #1 to Shaft #2 is ongoing, contractor is working 2 shifts


Shaft #2   Located west of house #3458 Golf Club Road

-no work at this location, single lane of traffic is open to residents at this location.


 Shaft #3      Golf Club Road and Trinity Church Road

-the contractor is continuing to mobilize the Microtunneling equipment to this location   


Shaft #4     Dickenson Road and Nebo Road

-the contractor will be drilling and breaking rock to advance the starter tunnel


Shaft #5 - Dickenson Road, approximately 385m east of Glover Rd

-the contractor is scheduled to complete excavating the rock from the shaft today


Shaft #6    Dickenson Road and Nebo Road

-no work scheduled at this location


Maintenance Hole 32A   Dickenson Road and Glover Road

-The drill rig will move to this location today and begin drilling for the remainder of this week


Maintenance Hole 33A  Dickenson Road between Trinity Church Road and Glover Road

-no further work at this location this week


Open Cut Sewers – Miles Road to Upper James

-Subcontractor is installing the sewer pipe in the open cut trench in the vicinity of French Road and Dickenson on the west side  


All road closures still remain in effect, Miles Road to Upper James on Dickenson is closed to thru traffic, travel is still open for residents, city services, EMS and school buses. 


Communication is being made with city services, EMS and school buses when the closure points are moved as the work progressed westerly towards Upper James.

13 views0 comments

Comments


bottom of page