Dickenson Sanitary Sewer Weekly Schedule



Here is the schedule for this week: 

Shaft #1    Regional Road 56 and Golf Club Road

-tunneling from shaft #1 to Shaft #2 is ongoing, contractor is working 2 shifts.  They have now passed MH43A (approx. 716 lm west of RR56)

Shaft #2   Located west of house #3458 Golf Club Road

-no work at this location, single lane of traffic is open to residents at this location.

 Shaft #3      Golf Club Road and Trinity Church Road

-the contractor is continuing to mobilize the Micro-tunneling equipment to this location   

Shaft #4     Dickenson Road and Nebo Road

-the contractor is waiting on repairs to the equipment, work will resume once repairs are completed (no time line indicated on repair time)

Shaft #5 - Dickenson Road, approximately 385m east of Glover Rd

-no work scheduled at this location

Shaft #6    Dickenson Road and Nebo Road

-no work scheduled at this location

Maintenance Hole 32A   Dickenson Road and Glover Road

-no further work at this location this week

Maintenance Hole 33A  Dickenson Road between Trinity Church Road and Glover Road

-no further work at this location this week

Maintenance Hole 26A  Dickenson Road between Miles Rd and  Nebo Road

-no further work at this location this week

Maintenance Hole 27A  Dickenson Road between Miles Rd and Nebo Road

- Drilling has stopped due to equipment breakdown.  Repairs will be 2 weeks in duration

Open Cut Sewers – Miles Road to Upper James

-Subcontractor is installing the sewer pipe in the open cut trench in the vicinity of #8456 and #8444 Dickenson

All road closures still remain in effect, Miles Road to Upper James on Dickenson is closed to thru traffic, travel is still open for residents, city services, EMS and school buses.  Communication is being made with city services, EMS and school buses when the closure points are moved as the work progressed westerly towards Upper James.   