Here is the schedule for this week for the Dickenson Sanitary Sewer work ongoing:
Shaft #1 Regional Road 56 and Golf Club Road
-no work at this location, single lane of traffic is open to residents at this location.
Shaft #3 Golf Club Road and Trinity Church Road
-no work is scheduled at this location.
Shaft #4 Dickenson Road and Nebo Road
-working on starter tunnel installation continues all week
Shaft #5 - Dickenson Road, approximately 385m east of Glover Rd
-working on drilling the concrete secant piles for the shaft construction
Shaft #6 Dickenson Road and Nebo Road
-no work scheduled at this location
Open Cut Sewers – Miles Road to Upper James
-Subcontractor is installing the sewer pipe in the open cut trench (currently working between #8250 and #8136 Dickenson Road).
All road closures still remain in effect, Miles Road to Upper James on Dickenson is closed to thru traffic, travel is still open for residents, city services, EMS and school buses. Communication is being made with city services, EMS and school buses when the closure points are moved as the work progressed westerly towards Upper James.